# Progress — orchestrator_16

## Current Status
Last visited: 2026-10-02T06:37:20Z
- [x] Survey phase: explore existing client/webapp code and structure for client/web_pc/
- [x] Merge survey reports & produce PROJECT.md
- [x] Dual Track: E2E Test Suite Creation & TEST_READY.md published (64/64 tests ready)
- [ ] Milestone 1: PC Desktop Web Client (`client/web_pc/`)
  - [x] Iteration 1: worker_m1 implemented, reviewers caught 3 runtime browser defects (Gate FAIL)
  - [x] Iteration 2: worker_iter2 resolved 3 defects, reviewer_iter2_2 APPROVED, reviewer_iter2_1 noted CSS asset 404
  - [x] Iteration 3:
    - [x] worker_iter3 fixing pc_hud.css:243 asset URL and serve_web_pc.py fallback routing (100% verified)
- [x] Succession to orchestrator_18 upon worker_iter3 completion (Spawn count: 16/16)
- [ ] Final Milestone: 100% E2E Pass & Coverage Hardening
- [ ] Report Victory to Sentinel

## Iteration Status
Current iteration: 3 / 32